Kohtz
1-30-03
|
|
|
|
Kohtz
1-30-03
|
|
|
|
Kohtz
1-30-03
|
|
|
|
Kohtz
1-9-03
Finishing Exterior Stone Work |
|
|
|
Kohtz
1-3-03
Fireplace Stone Completed |
|
|
|
|
Kohtz
12-5-02
Garage Door Installed |
|
|
|
Kohtz
12-5-02
Ready for Plaster |
|
|
|
KOHTZ
10-3-02
GARAGE FLOOR POURED |
|
|
|
KOHTZ
10-3-02
BASEMENT FLOOR POURED |
|
|
|
KOHTZ
10-3-02
BASEMENT BRACED |
|
|
|
|
KOHTZ
10-9-02
BRIAN'S CREW HAS BEGUN INTALLING THE DECK
|
|
|
|
KOHTZ
10-9-02
FRAMING CREW HAS ARRIVED |
|
|
|
KOHTZ
10-9-02
DECK IS BEING BUILT |
|
|
|
KOHTZ
10-18-02
FRAMING PROGRESS.
|
|
|
|
KOHTZ
10-25-02
FRAMING IN PROGRESS |
|
|
|
|
KOHTZ
10-25-02
FRAMING IN PROGRESS |
|
|
|
KOHTZ
10-25-02
FRAMING IN PROGRESS |
|
|
|
KOHTZ
11-11-02
FRAMING COMPLETE |
|
|
|
KOHTZ
11-11-02
INTERIOR FRAMING COMPLETE |
|
|
|
KOHTZ
11-11-02
VIEW OF WINDOWS IN REAR OF HOME |
|
|
|
|
KOHTZ
11-11-02
BASEMENT STAIRS ARE IN |
|
|
|
KOHTZ
11-18-02
MECHANICAL SUBS WORKING ON ROUGH-INS |
|
|
|
KOHTZ
11-18-02
SIDING BEING INSTALLED TODAY |
|
|
|
KOHTZ
9-5-02
FOUNDATION |
|
|
|
KOHTZ
9-5-02
FOUNDATION |
|
|
|
|
KOHTZ
9-5-02
FOUNDATION |
|
|
|
KOHTZ
9-5-02
FOUNDATION |
|
|
|
KOHTZ
8-28-02
FOOTINGS |
|
|
|
KOHTZ
8-28-02
CLOSE UP FOOTING WORK |
|
|
|
KOHTZ
8-28-02
CREW INSTALLING SUMP TILE |
|
|