GEHNER |
|
8-28-02
1ST FLOOR FRAMING |
|
|
|
|
|
|
|
|
|
|
GEHNER |
|
8-28-02
2 X 6 WALL CONSTRUCTION |
|
|
|
|
|
|
|
|
|
|
GEHNER |
|
8-28-02
BASEMENT POURED
|
|
|
|
|
|
|
|
|
|
|
GEHNER |
|
8-28-02
NOTE: CORNER POSTS BUILT TO ALLOW INSULATION IN ALL CORNERS |
|
|
|
|
|
|
|
|
|
|
GEHNER |
|
9-5-02
VIEW OF FAMILY ROOM W/CEILING |
|
|
|
|
|
|
|
|
|
|
GEHNER |
|
9-5-02
FRAMING 2ND STORY |
|
|
|
|
|
|
|
|
|
|
GEHNER |
|
9-5-02
VIEW OF 3-CAR GARAGE |
|
|
|
|
|
|
|
|
|
|
GEHNER |
|
9-5-02
VIEW OF INTERIOR WALL FRAMING |
|
|
|
|
|
|
|
|
|
|
GEHNER |
|
9-5-02
VIEW OF MID-LEVEL DEN FRAMING |
|
|
|
|
|
|
|
|
|
|
GEHNER |
|
9-12-02
VIEW OF SIDE/MID-LEVEL DENS |
|
|
|
|
|
|
|
|
|
|
GEHNER |
|
9-12-02
ROOF FRAMING IN PROGRESS |
|
|
|
|
|
|
|
|
|
|
GEHNER |
|
9-12-02
FRONT ELEVATION |
|
|
|
|
|
|
|
|
|
|
GEHNER |
|
9-20-02
ROOF ALMOST COMPLETE
WINDOWS IN |
|
|
|
|
|
|
|
|
|
|
GEHNER |
|
9-20-02
FRAMERS FINISHING UP INSIDE
|
|
|
|
|
|
|
|
|
|
|
GEHNER |
|
9-20-02
MID-LEVEL DEN |
|
|
|
|
|
|
|
|
|
|
GEHNER
10-3-02 |
|
SIDING BEING INSTALLED |
|
|
|
|
|
|
|
|
|
|
GEHNER
10-3-02 |
|
GARAGE FLOOR POURED |
|
|
|
|
|
|
|
|
|
|
GEHNER
10-8-02 |
|
SIDING FINISHED ON FRONT OF HOUSE |
|
|
|
|
|
|
|
|
|
|
GEHNER
10-8-02 |
|
SIDING COMPLETED ON SIDE OF HOUSE |
|
|
|
|
|
|
|
|
|
|
GEHNER
10-8-02 |
|
COMPLETING SIDING ON SIDE AND REAR OF HOUSE |
|
|
|
|
|
|
|
|
|
|
GEHNER
10-8-02 |
|
ELECTRICIAN, DENNIS OF YOUNG ELECTRIC, WORKING ON ELECTRICAL TRIM PHASE |
|
|
|
|
|
|
|
|
|
|
GEHNER
10-11-02 |
|
SIDING WORK COMPETE |
|
|
|
|
|
|
|
|
|
|
GEHNER
10-11-02 |
|
LARGE WALK-IN CLOSET ADDED IN BEDROOM FROM SPACE OVER GARAGE |
|
|
|
|
|
|
|
|
|
|
GEHNER
10-11-02 |
|
CLOSET EXPANDED IN SPARE BEDROOM |
|
|
|
|
|
|
|
|
|
|
GEHNER
10-18-02 |
|
CONCRETE DRIVEWAY BEING POURED TODAY |
|
|
|
|
|
|
|
|
|
|
GEHNER
10-18-02 |
|
FRONT PORCH READY FOR CONCRETE |
|
|
|
|
|
|
|
|
|
|
GEHNER
10-18-02 |
|
WAGENBACH CONCRETE POURING DRIVEWAY |
|
|
|
|
|
|
|
|
|
|
GEHNER
11-11-02 |
|
BLUEBOARD INSTALLED |
|
|
|
|
|
|
|
|
|
|
GEHNER
11-11-02 |
|
PLASTER IN PROGRESS |
|
|
|
|
|
|
|
|
|
|
GEHNER
11-11-02 |
|
LIVING ROOM BEING PLASTERED |
|
|
|
|
|
|
|
|
|
|
GEHNER
11-18-02 |
|
GUTTERS INSTALLED TODAY |
|
|
|
|
|
|
|